5 March 2026 Dearborn County Regional Sewer District Meeting Notes
This was a 2 hour 40min meeting
Board
Doug Baer Treasurer County Board of Health 12-31-2027
Brett Fehrman VP & Secretary City of Aurora 12-31-2025 - Acting Chairman
Steward Cline Board County Commissioners 12-31-2025
Russell Beiersdorder Board County Commissioners 12-31-2025
Jeff Stenger Board County Council 12-31-2028
ABSENT: Steve Renihan and Jeff Bittner and Attorney, Frank Kramer
Also present: Hrezo Engineering- Mike, Christy, and Kevin
Stenger read the Public Access Statement as legally required.
Minutes: February 19th Meeting- Approved
Public Comment:
Lynn Allen ( Council Pres in Moores Hill) and Rafferty Development (for Dollar General) - Kevin was going over the plan for getting the sewer line across SR350 for Moores Hill residents.
Cline asked about the manhole for a single use.
Mike explained that it is there to allow options. The cost for the lateral would be a cost to the requester.
Cline thought there might be a different strategic solution that might not be all DCRSD cost. He was trying to get more gravity feed in the plan.They run out of gravity when they hit Hogan Hill Rd.
Doug Baer- If we expend these funds, whose customers are these. We can’t be spending these funds and giving it away.
Stenger was looking at the gravity options to have less pumps and problems. Take $7,000 off as there is an existing manhole right there.
Cline- There has to be an interlocal agreement for a bulk rate for the homes. The Dollar General takes more. And it will take longer. The couple with the house restoration need an answer in 4-6 weeks.
Doug Baer- If sewers are available, they should be a primary option. Could maybe do a temp pump and haul if the tank is watertight.
The owner reminded them that it would be difficult to sell with pump and haul.
Jeff Hughes Redevelopment Moores Hill- They could sell it with a septic tank- and the new buyer could tap in to the sewer when it comes.Final idea was to see what it would cost for themto put a lateral just for them to go under SR350. If that fails to be able to be done then Baer would have to check with Atty and health officer.
Dollar General wants to connect- starting to build in Sept.There is a manhole across SR350 for them too. There would need to be an interlocal and there is a time frame when they would end up getting annexed. Baer asked about wetland characteristics there. Lift station is 25 ft deep. They will definitely need sewer. Check with soil and water district on the wetland woods area.
Committee to look at the Moores Hill interlocal- there will be 3 from DCRSD and 2-3 from Moores Hill.
MANUFACTURER REP Mr Layton FROM COVALENT- for grinder pumps. He wants the project to be successful. They do secondary homeowner training and also for contractors and the pumps. You want have a sealed system and not use old piping. You get infiltration with old pipes. Don’t just cut off the pipe at the septic inlet and pipe to the grinder. Baer said this is for homeowners. E1 system is 20-25 yer lifetime. Board discussed that we already have an installer program using an approved list of installers.
Meinders noted that they will have to be tight in Dillsboro as they will be costing more to treat infiltration with the bulk rate. E-1 pump - Layton said they don’t have blockages much. The board thinks these instructions and training are good- and they are glad to know about the problem with the piping from the houses. Date for warranty is the date of substantial completion of the project. 2 year warranty for factory defects.
Project Updates: Christy reports Guilford building is still ok- boring under RR tracks and march and April.
Dillsboro- Headworks wiring and electronics not done yet with all the rain. Lift station next and pump installation. Will need to get the specs updated and plumbers they recommended updated too. They want to be sure downspouts and sump pups are not going thru the grinder pumps. This would protect the DCRSD investment. With a pressure check we also have a baseline. Derek Walker should expect flow to Dillsboro in a month per Meinders. SEIData is starting up first.
Baer said we do not have user agreements signed yet- NEEDS to be done ASAP and the agreements updated. Meinders contract has him giving them the agreement to sign before he puts the grinder in and hook them up. The gas station owner is ready to hook up now. Magnetic meter and runtime meters are to have current pricing and availability from Hrezo.
Christy said the users agreement is in the asset management plan in their folders.
Cline - will ask Kramer if they can put a penalty on the bill for sumo pumps, downspouts etc. It should be big enough to get people’s attention. Board agreed.
Mike Hrezo has things for claims that were in packet. Wants to be sure we are good to go on these that were submitted last week:
Payout 3- Guilford- $ 283,116.63
Payout 4 - Dillsboro Lake Dildear - $239,712 (retainage is taken out of that)
No action required on these tonight. This is back up verification of things already. Some estimates already.
Revised chainlink fence cost. Only material- no labor. If cost goes up- the insurance costs go up at end via auditing the increases. There is an additional bond. Per Meinders. Mike Hrezo was citing cost issues and variability with tariffs. Engineers were approved to bring these 2 change orders in next meeting.
Change orders- needed a floodlight and receptacle at the control panel for additional price. Approved.
Guilford- 3 air release valves $5,883 each. Water line casing crossing to bore it. The RR license question- we need them to sign it at the correct time when construction is ready to go. Have a 60 day window. Weather is the issue.RR lady will sign it in mid March per Meinders. Timing is about 2 days. Have to pay a RR flagger to watch them for that time. Approved.
Also another light and outlet like at Dillsboro. $2,755.75 Approved
PAY #5- for next meeting’s claims-to them so they can review.
Kevin also provided at Cline’s request a set of fees for customer requests for the board to review.
Christy had standard operating procedures for asset management plan. Draft PER is continuing to be refined. Application for SRF ( State Revolving Fund) has to be received by the end of the month.Onsite expansion of High Ridge Plant is at $3.2-5.3 million. There were estimates for $2.5-4.4 million grant and debt service. The application has to be ready by next meeting and has to be approved then. Approved for her to complete that. 50 people are still paying availability fees and others on the other side who are available. They would have to start a rate study for this eventually.
RFP Discussion and Review.
Motions to Proceed with contract negotiations to hire CH& M as our contractor to run the DCRSD. 4 AYES and 1 Nay (Cline wanted to negotiate with contractor first) Approved
Office Update:
Baer and Cline brought out budget for board to review. Working with Christy for asset management. And items needed for the SRF grant.
Baer showed change orders and contingency funds. Got some interest too- almost $30,000. Using it for overages from change orders. Trying to work the contingency out. $777,000 contingency. Guilford had a much bigger contingency there. Concrete bridge still needed for Gas co. Just wanted everyone up to speed on money.
Cline wants to set money aside for certain items. And not use operating budget. Agreed.
Claims:
Lake Dildear $243,118.01
Guilford $288,932.87
Operating Claims $16,223.25 All APPROVED
Cline wanted to have the contract for Jeff Meinders with his and Clines comments and markups for next meeting.
Discretion of the Board: Brett Fehrman- apologized for the length of the meeting.
Adjourn: 7:40 PM
Christine Brauer Mueller
Lawrenceburg Township