19 November 2026 Dearborn County Regional Sewer District Meeting Notes
Present:
Steve Renihan, President, Brett Fehrman, Jeff Bittner, Russell Beiersdorder, and Jeff Stenger
ABSENT: Steward Cline and Doug Baer and Board Attorney - Frank Kramer
Also present: Christy and Kevin of Hrezo Engineering, and Jeff Meinders
Stenger read the Public Access Statement as legally required.
Minutes: November 5th Approved
Treasurers report reviewed- Financials prepared by accountant - Approved
Conrad Gerdes- first place west of Dillsboro - gravity there but 1000 ft or less. Twin Oaks area has first man hole. Jeff Meinders offered to meet with him there and see if they can get to the man hole.It would be an addition to our agreement and use the Hoosier Hills water meter as sewer meter. Otherwise go back to SEIData. Longer route perhaps. He’s 91 and wants to get it done before he dies. He gave Meinders his phone number.
Project Updates:
Guilford- Kevin - Earth Tek at the site next week. Supposed to be this week.- Renihan - stay on them. See if they can get maintenance manual. Reached out to IDEM to see where they can discharge the groundwater and what permits are required. One well between both excavations. 2 wells is what Jeff Meinders recommended. Doing nothing different Tham any field tile- Not breaching the tank area either. No different than roof downspouts. IDEM did not mention groundwater with Chaffee’s designs. Steward sent out an email where he said we need to pace ourselves on these questions. Perimeter drain is going to have to go outside the potential fence. No fence saves them $29,000. Easier mowing. Security on lids electric panels and controls and also not much public even out there. Fence makes access difficult to any work needed. Stenger looking at 2nd NPDES discharge permit? Christy - as soon as you daylight groundwater you need a discharge permit. Even if it’s a tile drain? Yes- per Christy- but its a different kind of permit. She’s waiting on an answer from that. Hold until she gets that info. Field tiles not needed if we are doing the permit.
Going to dewater those 2 tanks to half full- so there is some place to hold wastewater until they hook on some houses. Then they seed it.
Guilford line run out 150 ft to the Fire Dept and needs 400 ft more to get there. $18/ft = $7,200. DCRC approved paying to extend that line 400 ft more to the Fire Dept. They already have a grinder pump. They will be another customer. There will be a change order from Christy on this.
Moores Hill- They need a permission letter for the Dollar General. Question as to whether they annex it or not. They should have an interlocal agreement if it’s out territory until it’s annexed. Seems they would want annex for the tax.
Dillsboro- Christy evaluated the pumping station. If bypass in- 5 of these E-1 pumps zones would then require higher heads. Hydraulically it will work according to her calculations. Lift station actually creates the cleansing. REMC only does air cooled generator for residential- so something different is needed here. Russell Beiersdorfer doesn’t tink we need the generator. Jeff Bittner- said you can check with Atlas to see about the specs. Bypass would eliminate the need for a generator. Stenger noted the issues with the bypass to consider- but would have to turn it off and on during an outage. Meinders said not urgent as there is now 12 sewered homes on the line. Before it would have been easier to hook up.
High Ridge Plant gets seeded from Milan when they need that.
They calculated the Pine Run Trailer Park I and I. No significant rain in that time period. 83 gal per day of I and I. May need to see that again later when more rain. Discussion of the various points in the video of the line.
Christy- need to get a meter calibrated at the plant. They need to get password. They need another flowmeter to get better readings got help keep our limits down. No cost estimate yet from DL Anderson Co. We need a spare pump at the treatment plant. All pumps are working correctly at this time. One violation in early June and none since and all mechanical work finished in October. If a pump goes down we need an immediate exchange if something happens. No more issue with IDEM agreed order there. Sanitary sewer overflow was in a customer's grinder pump in their yard. This should not be under the plant’s order. Renihan wants to get it all done and no violations for a year to get out from under this. Doug Price puts readings in twice a month- not daily and it goes straight to IDEM.
Christy had the exact list that IDEM is looking for. And they need to get the costs. The agreed order will not be held up by these things. They will wait on this. Put more info in the report so it sows we are being proactive. Quarterly reports are needed. They were happy we fixed all the candle issues- so that comes out. Get this quotes. Kevin- ask Frank to fix the language on the 12 months portion of the report.
They come out every 3 years.
New Business: none
Office Update: Verified 10 liens paid in fall taxes. 2 unpaid, and one has a balance to pay. 5 customers hooked on 11/9 and 4 on 11/18 and one in Guilford. He texts the address to each to Kelly per Jeff Meinders.
Kelly to do an invoice for $35 for NSF ck fee from customer. Approved.
Claims: $36.72 billing adjustment to new owner- Approved
$2,648.36 Lake Dilldear -Approved
$124,285.41 Guilford- Approved
$11,512.42 operating claims- Approved
Adjourn: 6:35 PM
Christine Brauer Mueller
Lawrenceburg Township